Project Overview

Orange and Rockland (O&R) is proposing a new 138-34.5/13.2 kilovolt (kV) substation at 2473 Route 17A in Goshen to replace the existing South Goshen Substation. The existing facility is over 50 years old, utilizes obsolete infrastructure, is nearing its maximum load capacity, and does not meet current O&R design standards. The Project will increase service reliability and capacity for local customers. The upgrade will increase the grid's capacity to handle Distributed Energy Resources (DER), such as local community solar projects, aligning with New York’s renewable energy goals.

The proposed Goshen Substation will operate at 138 kV and features a 6-breaker ring bus configuration, three transformer banks, a 12-circuit switchgear, and a modern control house. The new substation will connect to the adjacent 138 kV Line 27 west of Route 17A.  

Key Dates

Fall 2026

Open House

Spring 2027

File Article VIII Application

Winter 2027/
Spring 2028

Permitting Complete

Spring 2028

Construction Start

Summer 2029

Project Complete